YOU DID NOT WAKE UP TODAY TO BE MEDIOCRE.
--Your friends at LectureNotes
Close

Previous Year Exam Questions for CONSTRUCTION EQUIPMENTS PLANNING AND MANAGEMENT - CEPM of 2018 - CEC by Bput Toppers

  • CONSTRUCTION EQUIPMENTS PLANNING AND MANAGEMENT - CEPM
  • 2018
  • PYQ
  • Biju Patnaik University of Technology Rourkela Odisha - BPUT
  • Civil Engineering
  • B.Tech
  • 409 Views
  • 10 Offline Downloads
  • Uploaded 1 year ago
0 User(s)
Download PDFOrder Printed Copy

Share it with your friends

Leave your Comments

Text from page-1

Registration No : Total Number of Pages : 02 B.Tech. PECI5408 8th Semester Regular / Back Examination 2017-18 CONSTRUCTION EQUIPMENTS, PLANNING AND MANAGEMENT BRANCH : CIVIL Time : 3 Hours Max Marks : 70 Q.CODE : C110 Answer Question No.1 which is compulsory and any five from the rest. The figures in the right hand margin indicate marks. Q1 Answer the following questions : What is the need of equipment management in site? What are all the parts of a scrapers? List out some hoisting equipments. List out the major quality control methods. What do you mean by TQM? What are the different types of Floats? What are safety audits? What is meant by earnest money deposit? What is a bid? What is turn key contract? (2 x 10) Enumerate various types of equipment required for : i. Compaction ii. Dewatering and pumping (10) a) Explain the advantages and use of a conveyor in construction projects. (5) b) Explain the detail of the importance of concrete mixture in construction work. (5) a) What are the legal requirements regarding safety as applicable to construction site and the construction industry? How are safety provisions covered in contract document ? (6) (5) b) What do you mean by bill of quantity and how is it important for a construction project? Discuss how disputes are solved in the process of Arbitration. a) b) What are the contents of a tender document? Describe. Enumerate the complete tendering procedure with illustrations. (5) (5) a) b) c) d) e) f) g) h) i) j) Q2 Q3 Q4 b) Q5 Q6 a) (4) (5)

Text from page-2

Q7 For the data given in the table, Find (a) Critical path and earliest time to complete the project, and (b) early and late start, early and late finish, for all Q8 a) b) c) d) Activity A Duration(weeks) 5 Predecessor(s) --- Successor(s) B,C B C D E F G H I J K L 6 8 6 7 7 7 5 12 11 11 8 A A B B,C B,C D F F E G,I H,J D,E,F E,F G J H,I K L K L ----- Write short answer on any TWO : Derrick crane Quality control in construction Item rate contract Validity of a contract (10) (5 x 2)